Is low lift or high lift grouting specified? Is vertical reinforcement installed per project documents? Is jamb, lintel, bond beam reinforcement installed per project documents? Are rebar positioners required per project documents? Are the masonry cells clean for grouting? Does the grout meet the project specifications ? (Approved Mix) Are cleanouts installed? (Grout pour height greater that 5 feet) Have grout samples been made? Is the contractor consolidating the grout? Does the slump of the grout meet the project specifications Is the weather protection procedures being followed per project specifications?